Monday, April 1, 2013

The first Ten Months

The following graphs provide some insight into the performance of my 2kW solar system. It's operation has been trouble free and the results are in line with our expectations, and the data I've collected so far confirms that with another 3kW my electricity CO$T will be all but eliminated. I already have my two 1.5kW inverters ready to be mounted next to the current unit, all I need to organise is an additional 16-20 panels and their installation.

Graph 1 - My total usage in the fifteen months PRIOR to the system install.


Graph 2 - Inverter Output and Power Export
This graph portrays a significant factor not generally considered by solar system users: how much of my solar generated watts are actually directly powering my home needs? In my case the blue area represents true offset, i.e. I've used a lot of what I've generated. The smaller red area is what I've sold back to the grid. While my objective is to minimise the red area and thus increase the blue area, this is only because my "feed-in" return is less than the current cost of electricity, and sadly, always will be.
Those who (in South Australia) connected their system in 2011 and before would have a different objective, as their "feed-in" return is set way higher than the cost of the purchased electricity, so someone in that situation would want the red area to intrude further upward and reduce the blue area. This high "feed-in" tariff has been a contentious issue with electricity consumers generally, and also with the political interests who've reacted to the claim that the generous "feed-in" provisions have had an impact on the rising price of electricity here.
As I mentioned above, though, my objective is to consume as much of what my system produces, as this represents a greater saving.
Ultimately, I'm hoping to collect some of my solar D.C. power and store it in a battery bank so I can use that stored electricity to continue powering my inverters when the sun goes down...thus saving me even more.


Graph 3 - Post Solar Charged Consumption (this is what I paid for)


Graph 4 - Post Solar Total Consumption

Important note: the "dates" shown above are the dates I took my readings, therefore the reading represents consumption/production during the month before, so clearly the "1-April-2013" reading represents "March 2013" usage, etc.

Wednesday, June 13, 2012

On the grid!

Right on schedule my "net" meter arrived early this morning and within half an hour was installed
and monitoring my meagre 600W contribution,
due to overcast conditions.

Thursday, May 3, 2012

Installed

Right on schedule the install team arrived to a crystal clear, but really cold morning, perfect for the outdoor roofwork.
Cabling went well in the end, after original wall cavity path proved impassable, fortunately my previously installed A/C wiring ducts provided the perfect solution. My additional DC wiring (for proposed batteries) was also easily accomodated, just have to arrange the necessary switch and then scrounge an old refridgerator to serve as a battery cabinet.
Now we have to wait until mid June for the "net" meter which measures and records both (consumed) power from the grid [import] and (generated) power put into the grid [export]. Until then the system is just sitting idle....
The installer was telling us his 3kW system was producing approx. $500 - $800 per quarter of credit (I didn't ask but reasonably suspect he's getting the old 54c/kWh feedin tariff).
Oh well, as long as our electricity bill reduces significantly it will be worthwhile, later, when we've pocketed some savings we'll move to the next "phase" and install another 3kW system and really put a dent in the bill, if not eliminate it altogether.

Wednesday, April 25, 2012

Installation Date

Notwithstanding inclement weather, my panels and inverter will be installed on May 3rd, unfortunately the "net" meter (which tracks both my consumption and production separately) won't arrive until late May. My system will still be connected to the "grid" and feed any electricity produced into it, I just won't have any (official) record of it.

Thursday, April 19, 2012

While I was waiting

Having a break in the Barossa and happened upon this substantial installation at Jacob's Creek Winery.
The panels appear to be ~200W units and each array is 5x14=70 panels, giving a total combined output in the vicinity of 25-30kW!
To ensure maximum output they track the sun, too.

Thursday, April 5, 2012

Always Learning!

So my installer rang me to see if I'd received any communication from my electricity distributor, which I had (see previous post). He was concerned as, unusually, his submission for approval wasn't responded to by the distributor. Turns out my application for a "peak" capacity of 5kW may be the sticking point, procedurally, as he usually gets his approvals returned "same day" (and without the consumer's involvement). It's possibly due to new attitudes, policy wise, about larger systems?
Nevertheless, his call got me thinking about other "approval" I hadn't paid particular attention to, mainly, in this instance, "Development Approval" (in South Australia). I remembered hearing some time ago that some people were running into strife with their Council Building Inspectors because they hadn't sought approval for the installation of their solar panels, and this had consequences. A quick check of my council website failed to identify any specific requirements for approval. On the contrary, a Council Fact Sheet (last updated January 2012) identified information about "Schedule 3 - Acts and activities which are not development" which, in section 15 clearly set out the exemption that applies to Solar Panel Installation:

(The following acts or activities are excluded from the definition ofdevelopment (other than in respect of a State heritage place, or as otherwiseindicated below).)

15—Solar photovoltaic panels
        (1)         Subject tosubclause (2), the installation, alteration, repair or maintenance of adesignated photovoltaic system on the roof of a building.
        (2)         Subclause (1)does not apply if the place where the designated photovoltaic system isinstalled is a local heritage place if, when installed, it is able to be seenby a person standing at ground level in a public street.
        (3)         In thisclause—
designated photovoltaic system means—
            (a)         aphotovoltaic system comprising solar photovoltaic panels that have a totalweight not exceeding 100 kilograms; or
            (b)         aphotovoltaic system comprising solar photovoltaic panels that have a totalweight exceeding 100 kilograms if—
                  (i)        the weight load is distributed so that it does not exceed100 kilograms at any 1 point of attachment to the roof; and
                  (ii)        the panels (and any associated components) do notoverhang any part of the roof; and
                  (iii)        the panels are fitted parallel to the roof with theunderside surface of the panels being not more than 100 millimetres abovethe surface of the roof; and
                  (iv)        the panels are installed by a person who holds anaccreditation under a scheme recognised by the Minister for the purposes ofthis paragraph.  

Application Progress

Today I've received email from my electricity distributor advising...
"Your application to install a Small Embedded Generator at (my suburb), has been received"
Just have to sign the T&C's and return it to them, and we move a step closer....